Forum Discussion
Grit_dog
Nov 30, 2017Navigator III
troubledwaters wrote:Lynnmor wrote:There is no way to verify concrete meets the requirements of the specs when it is poured. The only way to verify the concrete meets the requirements is to make cylinders at the time of the pour and break them 28 days later.
3. A brand new bridge has concrete that didn't pass inspection and will be completely torn out and replaced. I guess the concrete wasn't inspected at the time it was poured.
You guys are funny. Neither have enough info to speculate on this.
BTW compressive strength is only 1 “spec” that it needs to meet and a lot of the “specs” are verified at the time of placement. Some are even verified before the job starts!
About RV Tips & Tricks
Looking for advice before your next adventure? Look no further.25,178 PostsLatest Activity: Dec 20, 2025