Forum Discussion
ScottG
Jun 14, 2017Nomad
MrWizard wrote:
NEC is for the service drop panel to be grounded
Back when I did new home construction
We drove the ground rod next to the house right where the service drop was located
And run the ground wire from the service drop to the driven ground
The wire run from the warehouse to the pole should be (3) wires for 120v
If there are 3 wires get somebody to check the connections
If you have SWR problems, I would start checking equipment an antenna grounds
Now they want dual ground rods even at the sub panels. Just went through inspection after installing an entire service. We put in a standard 100A RV panel and even that got two rods!
We put in two at the meter box, 2 at he main panel (actually a sub) and two at the RV port.
6 rods!!!
About Technical Issues
Having RV issues? Connect with others who have been in your shoes.24,188 PostsLatest Activity: Jan 17, 2025