The current multiyear painting project
http://www.oregon.gov/ODOT/HWY/REGION2/pages/astoria_megler_bridge_painting_phase2.aspx
During one of the wind storms in the past year the bridge was closed briefly because the wind dislodged some of the sheet metal used to protect vehicles from painters above. There was also a closure when a tractor trailer tipped over part way due to wind.
Historic coastal bridges
5 yr North Bend bridge work
http://www.oregon.gov/ODOT/HWY/REGION2/pages/astoria_megler_bridge_painting_phase2.aspx
During one of the wind storms in the past year the bridge was closed briefly because the wind dislodged some of the sheet metal used to protect vehicles from painters above. There was also a closure when a tractor trailer tipped over part way due to wind.
Historic coastal bridges
5 yr North Bend bridge work