โNov-02-2017 08:40 AM
โNov-17-2017 04:00 AM
Not looking to get into arguing over whatever the detailed engineering specifics are. Just want a general idea how much concrete I'll be buying if I decide to concrete the barn floor.
Got what I need for now -- Thanks all!
โNov-17-2017 02:30 AM
Grit dog wrote:bid_time wrote:monkeygirl wrote:Really, no Flyash? Maybe you can tell me why that is seeing that every professional organization such as ACI, ASCE, FHA, ACPA, all recommend a minimum of 15% flyash and preferably 25%. And before you comment, maybe you should look up ASR (Alkali-Silica Reactivity). And we won't even talk about GGBFS which is also used at up to 40% cement replacement.
I am a concrete guy of 30 plus years... make sure it is straight cement content. NO FLY ASH ...
No fly ash because this is rvnet. The land of ex-experts who don't know what they're talking about....
I'm in trouble! I've placed probably a half million yards of concrete in bridges, roadways, water tanks and treatment structures and dams, all with fly ash or slag or other pozzolans. C rap. I've been doing it wrong. Can't believe I believed all those specifications and my grad level concrete structures and mix design courses!
โNov-17-2017 01:52 AM
allen8106 wrote:
I am now in the process of erecting a new building. A combination RV storage and work shop.
I had a 5" floor poured for my 10,500 lb 5er.
โNov-16-2017 07:16 PM
riven1950 wrote:ivylog wrote:
Glad you know so much. Last week I had a 12 yard concrete truck put the front tires on 48 hours old concrete...it was a front loader truck. 3000 psi concrete means when fully cured it will support 3,000 lbs / square inch. In 48 hours it's 25% cured. Do the math for a tire with 120 psi in it. In 5 days it's 35-40% cured.
I started to tell the OP 2 days but said 5 in hopes someone who has never poured concrete would not spout off.
PS: TT tires have closer to 60 psi in them. In the last 60 days I have pour aprox 50 yards
Not sure what the PSI in the tire as to do with it. Are you saying a loaded Concrete truck puts the same pressure on the concrete as an unloaded one because the tire PSI is the same? So a 4000 lb TT will have same effect as a 14,000 lb 5th wheeler as long as the tire pressure is the same? I think not.
All I suggested was that the OP do a google search for concrete cure rates and recommendations for driving on it. You try that and see how many people think it is wise to do as you said.
If it is my money I would err on the side of caution. You can do as you please.
โNov-16-2017 07:03 AM
โNov-14-2017 03:43 AM
Ivylog wrote:I couldn't agree more!
...This post is my opinion (free advice). It is not intended to influence anyone's judgment nor do I advocate anyone do what I propose...
โNov-13-2017 11:06 AM
ivylog wrote:
Glad you know so much. Last week I had a 12 yard concrete truck put the front tires on 48 hours old concrete...it was a front loader truck. 3000 psi concrete means when fully cured it will support 3,000 lbs / square inch. In 48 hours it's 25% cured. Do the math for a tire with 120 psi in it. In 5 days it's 35-40% cured.
I started to tell the OP 2 days but said 5 in hopes someone who has never poured concrete would not spout off.
PS: TT tires have closer to 60 psi in them. In the last 60 days I have pour aprox 50 yards
โNov-13-2017 06:28 AM
โNov-13-2017 04:13 AM
โNov-11-2017 10:01 PM
bid_time wrote:monkeygirl wrote:Really, no Flyash? Maybe you can tell me why that is seeing that every professional organization such as ACI, ASCE, FHA, ACPA, all recommend a minimum of 15% flyash and preferably 25%. And before you comment, maybe you should look up ASR (Alkali-Silica Reactivity). And we won't even talk about GGBFS which is also used at up to 40% cement replacement.
I am a concrete guy of 30 plus years... make sure it is straight cement content. NO FLY ASH ...
โNov-11-2017 09:55 PM
larry barnhart wrote:
I did our extension on the side of our driveway in 1998 doing 5" of concrete and 1/2" rebar at 20" square. I ran an 36 " pattern roller over for a design and saw cut at 9ft on the straight line from the roller. No cracks but last winter something happened that I can't explain. On one area the concrete had a dark look and has flaked in that area. I cured it as good as can be done. No idea what was the reason.
chevman
โNov-11-2017 07:53 AM
โNov-11-2017 07:29 AM
cummins2014 wrote:Cummins12V98 wrote:newman fulltimer wrote:
8 inches down the center drive on area 6 on non weight area
For a RV???
Thats what I was thinking. I have had two RV pads on two different homes here in Utah, so there is the freezing issue. Both pads were poured with 6 bag , and the standard 2x4 forming.
The first one in the late seventies did get some cracks, but held up well otherwise. The problem back then it seemed we just poured , with not enough expansion . My first one was 15 feet wide one expansion joint down the center, okay there ,but it was like around 50 feet long, with expansion joints around every 12 feet. Not enough, it has to expand.
My present RV pad is 80 feet from street to back of the house . Only 11 feet wide , expansion up the center ,and every 6 feet or so the length of it. So 5*1/2 x 6 foot sections. No cracks, other then where it cracked in the expansions. going on 18 years ,looks as good as it did new. Has had a 38' foot fifth wheel on it for the past 10 years. To add this driveway ,and RV pad was poured with fiber mess. No rebar.
โNov-11-2017 04:38 AM
riven1950 wrote:
Ivylog, Glad you are not doing my driveway. No way I would spend that kind of money and then park a 14K fiver on it after 5 days.