I'm in the planning stages of adding solar to my travel trailer.
I currently have a battery bank of two 6V flooded lead acid GC batteries in series that is 215 Ah 12 volts. I am planning on adding two more of the same batteries in series-parallel for a 430 Ah 12 volts (215 Ah usable) battery bank. I then plan to add 800 watts of solar. Right now I'm leaning toward using four of the Renogy 200 watt panels.
I plan to wire in parallel, as from what I've read, if I'll be camping in shaded/partial shaded spots, which I usually do, parallel gives better output in these conditions. However, if the panels have internal diodes, does this make this line of reasoning not applicable?
I'll then combine these at a combiner box. Is a combiner box necessary? Or can I just do a T-branch coupler, assuming the amp rating is high enough? And when run in parallel, am I correct in assuming I'll need a fuse/breaker at each positive cable from each individual panel? And if so, is there a combiner box that also has breakers?
From the combiner box, I believe I also need to have a properly rated breaker/fuse to the charge controller, right? And I am planning on a 60 amp MPPT charge controller, that should be correct for 800 watts panels, right?
From the charge controller, I'd need a final breaker/fuse between the controller and the battery, right?
And I'd be using proper gauged wire, based on run length and amperage at each station, probably 10 ga --> 4 ga --> 6 ga. I'd have to measure distances and consult an ampacity chart.
I'm planning on putting the charge controller in the front underneath storage compartment of my Grey Wolf 22MKSE, as this is the closest covered compartment to the batteries. I'm thinking actual line length would be about 5-7 feet from the charge controller to the battery. I don't know where the best place to put the combiner box. I'm thinking having it right next to the controller would be best, in order to cut down line length.
I'm pretty comfortable with electrical in general, but this will be my first go at solar, so please critique my plans and add any advice, it will be appreciated.
Thanks!
EDIT: I should add that the trailer came with a factory installed 50 watt panel with a piddly charge controller. I'll be completely removing this from the system entirely.
EDIT AGAIN: Oh, and what do I do about the AC-DC converter. Will the solar charge controller work seamlessly with this?
And I don't need an inverter at this time. The only thing I really need that is AC when I'm not plugged in is the air conditioning, which I would only use if I had shore or a generator
I currently have a battery bank of two 6V flooded lead acid GC batteries in series that is 215 Ah 12 volts. I am planning on adding two more of the same batteries in series-parallel for a 430 Ah 12 volts (215 Ah usable) battery bank. I then plan to add 800 watts of solar. Right now I'm leaning toward using four of the Renogy 200 watt panels.
I plan to wire in parallel, as from what I've read, if I'll be camping in shaded/partial shaded spots, which I usually do, parallel gives better output in these conditions. However, if the panels have internal diodes, does this make this line of reasoning not applicable?
I'll then combine these at a combiner box. Is a combiner box necessary? Or can I just do a T-branch coupler, assuming the amp rating is high enough? And when run in parallel, am I correct in assuming I'll need a fuse/breaker at each positive cable from each individual panel? And if so, is there a combiner box that also has breakers?
From the combiner box, I believe I also need to have a properly rated breaker/fuse to the charge controller, right? And I am planning on a 60 amp MPPT charge controller, that should be correct for 800 watts panels, right?
From the charge controller, I'd need a final breaker/fuse between the controller and the battery, right?
And I'd be using proper gauged wire, based on run length and amperage at each station, probably 10 ga --> 4 ga --> 6 ga. I'd have to measure distances and consult an ampacity chart.
I'm planning on putting the charge controller in the front underneath storage compartment of my Grey Wolf 22MKSE, as this is the closest covered compartment to the batteries. I'm thinking actual line length would be about 5-7 feet from the charge controller to the battery. I don't know where the best place to put the combiner box. I'm thinking having it right next to the controller would be best, in order to cut down line length.
I'm pretty comfortable with electrical in general, but this will be my first go at solar, so please critique my plans and add any advice, it will be appreciated.
Thanks!
EDIT: I should add that the trailer came with a factory installed 50 watt panel with a piddly charge controller. I'll be completely removing this from the system entirely.
EDIT AGAIN: Oh, and what do I do about the AC-DC converter. Will the solar charge controller work seamlessly with this?
And I don't need an inverter at this time. The only thing I really need that is AC when I'm not plugged in is the air conditioning, which I would only use if I had shore or a generator