Reisender wrote:
The BC hydro website digs into this a bit. Essentially the province doesn’t have a problem with generating capacity. But distribution and grid will adapt in the normal course of maintenance and up keep going forward to adapt to the changing load in neighborhoods etc.
Nailed it. Gen capacity is not (too much of) an issue in BC, especially once Site C comes online. We're at around 2,000 MW remaining capacity at peak usage, simplified math says 330,000 6kW home slow chargers. If charged overnight then virtually unlimited.
But we have a lot of neighborhoods still fed by single phase 12kV lines, and older substations are tapped out. Upgrading the entire province to 25kV will take a long time (took 5 years just to get rid of the last 3 4kV substations).
I fully support a 2-tier rate system with cheaper off-peak hours. However, if that means higher peak hour rates, then non-EV owners won't be happy.