It's hard to say how long one takes from from build start to ship date due to parallel stages of construction. I would categorize the assembly as framing build out, wall assembly, interior fabrication, interior assembly and external assembly. Each section cranks out parts so they are ready for the following phase that requires them. Once those assemblies are handed over, the next build is already underway before this one is finished. It's a balancing act of getting the parts in time without a wait yet not over delivering because there is only so much room in each section for staging. I think if production was halted and no assembled components were pre staged, it would take under two weeks to produce the first unit.