sjturbo wrote:
Thanks Niner! Actually the four Crowns are rated at 470ah. And according to the "Crown battery requirements, The Bible" that you linked me to it indicates a charge factor of 1.07 (107%) to be fully recharged. 470ah/2 = 235ah*107%=251.45ah for a complete recharge. I think I have that correct. It appears that none of the PD9200 converters can supply the 15.3vdc needed to top off the batteries, (more like 14.4 to 14.6vdc? with the pendant). I thought that is why MW suggested the Mega Watt power supply since the voltage can be adjusted to above 15vdc likely 15.5vdc. If I am boondocking and the only ac source I have is the Honda eu3000 I thought the Mega Watt was a logical alternative. I certainly like the solar idea and somewhere down the line I may invest in what you have noted. Until then the eu3000 is my only choice?
My Honda 3000 can run four Vector chargers at the same time doing a total of 130amps (on four batts) but if I try 135 amps the Honda pops its breaker so 130 is it with the Vectors (I think they have PF about 0.8 from some calculations I did a while back)
However, using my PF corrected PowerMax 100amper (does 103a) instead in the mix with two Vectors doing a total of 50a I can run 150a of charging with the Honda 3000 and not pop its breaker.
But I did modify the 100 amper to stay at 14.8v instead of dropping to 13.6 once the batts get to 14.6 so I get a faster charge. The PD80 amper is not PF corrected and needs a 20a circuit so it will use more of the Honda to make the 80a (expect more like 75a in real like with the PD due to a design "issue" they have unless mounted really close to the battery on really fat wires)
Your four batts could take two 80s worth of amps at 160a but the Honda couldn't run both at PF 0.7 It probably could run two 60s for 120a especially since that would likely be two 55a actual.
A battery will accept about 5a at 14.5v when it is at 90% SOC. So my rule is to stop the charge at 5 amps per batt when doing a 50-90. On two batts that would be when amps get down to 10 and with four batts, 20a.
So now you would swap to the MW and jack the voltage up to 15+ for the finish charge (inverter will alarm off at 15 so do it when you don't need the inverter---as noted the Honda 3000 will have lots to spare just running the MW so you can use the gen instead of the inverter anyway at that time)
Now your only problem is generator time past the time it took to do your 50-90. With 120a going in on four batts the 50-90 might take two hours. So you must keep the gen running long enough after that to do the top charge. I don't know how long that would take--another two hours?
How many amps will four batts accept at 15+ volts at over 90% SOC? Be more than 5a each at 90% at 14.5v. No idea. It will taper from 90-99% SOC whatever it starts at. Say it is 8a per batt for this math exercise--might be more than 8 really--so now you can do 4 x 8 =32a on four at 90%. If you try 40a and they will only take 32, then 32 is what you will see going in even if you try to shove in 40 :)